Infosys在阅读器中打开 / AI 翻译

TS8xxx - Building Automation · 0 次阅读

Monthly Time Scheduler Channel (nth day of the month)

With the Monthly Time Scheduler Channel (nth day of the month) it is possible to define a switching-event on a single day of the month in multiple months of the year.

Settings

Monthly Time Scheduler Channel (nth day of the month) 1:
  • Start: Time: Absolute start-time on a switching-day. The scheduler-channel will be active beginning with this time.
    Start: Sunrise + Offset: The scheduler-channel will be active beginning with the actual sunrise + offset (in minutes) on a switching-day.
    Start: Sunset + Offset: The scheduler-channel will be active beginning with the actual sunset + offset (in minutes) on a switching-day.
  • End: Time: Absolute start-time on a switching-day. The scheduler-channel will be active beginning with this time.
    End: Sunrise + Offset: The scheduler-channel will be inactive beginning with the actual sunrise + offset (in minutes) on a switching-day.
    End: Sunset + Offset: The scheduler-channel will be inactive beginning with the actual sunset + offset (in minutes) on a switching-day.

Series Model

  • Always on the nth of: The explicitly selectable switching day (1st...31st).
  • January...December: Selectable switching-months.

Behavior

Monthly Time Scheduler Channel (nth day of the month) 2:

In contrary to the daily and weekly scheduler-functions, the switching days are explicitly named. There is no periodicity to be calculated, which depends on the PLC-init-time.

If the daytime of the start is lower than the end, the scheduler channel will only be active from the start-time until the end-time of the switching-day. If the daytime of the end is lower than the start, the scheduler-channel will just work inversely. Entering the same time for both start and end would result in an undefined-state and will thus be regarded as an input-error.

It is also possible to use the sunrise/sunset function which will calculate both times for the switching-day together with an offset, which can be either positive or negative. These resulting start and end-time however are automatically delimited to the beginning (00:00:00:000) or the end of the day (23:59:59:999).

Scenes

Monthly Time Scheduler Channel (nth day of the month) 3:

On this screen the scenes can be entered, which shall be executed, when the scheduler-channel turns to either its active or inactive state.

Online

Monthly Time Scheduler Channel (nth day of the month) 4:

State

  • Value: Displays the current state of the scheduler-channel.
  • Remaining Time On: Remaining time in which the scheduler-channel is active.
  • Remaining Time Off: Remaining time in which the scheduler-channel is inactive.

State PLC Module

  • Execution State: Shows if the module is running or stopped.
  • Error: In case of an error, the error code and the error parameter are displayed in this box.
  • Start/Stop: Starts/stops the module.